The first hydroelectric power plant equipped by our company in Ukraine has started. This difficult and yet very interesting project included a total modernisation of the existing power plant. The modernisation concept was developed by our company. We used a Kaplan turbine with a vertical shaft and a rotor diameter of d = 1090 mm. The turbine operates at a nominal head of 3.5 - 3.7 meters.

The scope of equipment supply:
- a complete Kaplan turbine with a gearbox
- suction pipe
- a generator with an output of 132 kW / 1000 rpm
- hydraulic controller
- electrical equipment
- turbine control and automation
Turbine control and automation assemblies are based on Siemens components (control panel, network performance analyser, GSM module, Ethernet module). See the photo gallery.